Varying completion rates for Jeddah torrential drainage projects

The Jeddah Municipality revealed 7 rainwater drainage projects, with varying completion rates, in a number of targeted neighborhoods. Come closer.

The Municipality has already completed 11 rainwater drainage projects that targeted rainwater drainage for the Al-Tayseer area, the Al-Asala neighborhood, the construction of the Al-Salam estuary lift station, the rainwater drainage in the Al-Waha area, the rainwater drainage for the ball roundabout, the establishment of the secondary network surrounding the Al-Salam tunnel, as well as the rainwater drainage for sites surrounding the Peace Tunnel, draining rainwater to the sites surrounding the tunnel of Prince Majed Road with Hira Street, implementing quick solutions for 30 critical sites, and draining rainwater to sites surrounding the tunnel of King Abdullah Road with Al-Andalus Road.

Project completion rates

Paradise neighborhood

The completion rate in Al-Firdous neighborhood is 10.12%.

The project start date is 5-12- 2022.

– 15 months have passed.

Al-Huda neighborhood and part of Al-Ajaweed

The completion rate is 70.95%.

– Starting the project 3-13-2022.

The period since the launch of the project is 17 months.

Taiba neighborhood

The completion rate is 32.73%.

– Starting the project on 3-13-2022.

The period since the launch of the project is 17 months.

King Faisal Road (previously crossing continents)

The completion rate is 68.18%.

– The project started on 3-13-2022.

The period since the launch of the project is 17 months.

Muhammadiyah neighborhood

The completion rate is 52.69%.

– Project start 3-13-2022.

The period since the launch of the project is 17 months.

The Two Holy Mosques, part one

– The first part 10-10-2020.

The completion rate is 92.40%.

The period since the launch of the project is 34 months.

Al-Manar neighborhood

– Launched on 6-15-2020.

The completion rate is 96%.

– The period since the launch of the project is 38 months.

Groundwater reduction projects, the fourth stage

The completion rate is 86.73%.

– Launched on 11-2-2021.

20 months from the start of the project.

Reducing the surface water level (Phase IV)

The project was launched on 11-2-2021

The completion rate is 86.73%.

20 months from the start of the project.

Lowering the surface water level (second phase)

– Project start 2-18-2021

The completion rate is 95.35%.

20 months since the launch of the project.

Lowering the surface water level (third stage)

– Project start date 2-18-2021.

The completion rate is 83%.

– The period since the launch of the project to date is 24 months.